Excavation of core cut for the Nurek nydroelectric plant dam

  • Papers
  • Celebration of the 60th Anniversary of the Soviet Regime
  • Published:
Hydrotechnical Construction Aims and scope

Conclusions

  1. 1.

    Use of the tunneling method for excavating the cut for the dam core made it possible to place the loam in the dam core simultaneously with the preparatory work for blasting at the higher levels.

  2. 2.

    The distribution of the heap of blasted rock over a large area made it possible to use several excavators and, consequently, to reduce the time of completing the work.

  3. 3.

    In this method, it is not necessary to construct additional dropping places at the working levels.

This is a preview of subscription content, log in via an institution to check access.

Access this article

Price excludes VAT (USA)
Tax calculation will be finalised during checkout.

Instant access to the full article PDF.

Authors

Additional information

Translated from Gidrotekhnicheskoe Stroitel'stvo, No. 4, pp. 7–9, April, 1977.

Rights and permissions

Reprints and permissions

About this article

Cite this article

Bondar', I.Y., Bagdasarov, A.G. & Erofeev, E.V. Excavation of core cut for the Nurek nydroelectric plant dam. Hydrotechnical Construction 11, 345–347 (1977). https://doi.org/10.1007/BF02399245

Download citation

  • Issue Date:

  • DOI: https://doi.org/10.1007/BF02399245

Keywords

Navigation